BIBLIOGRAPHY
Canadian Standards Association, Risk Management: Guideline for
Decision-Makers, CAN/CSA-Q850-97.
Carnegie Mellon University, Continuous Risk Management Guidebook, 1996.
Standards Australia. Risk Management. AS/NZS 4360:1999
Transport Canada, Manual of Aeronautical Studies. TP13011E, 1998
Transport Canada, Regulatory Assessment Methodology, 1997.
Transport Canada, Fisheries and Oceans Canada. Risk-based Design Method for Aids to Navigation in the St. Lawrence River. TP13468E. 1999
Treasury Board Secretariat, Assessing Regulatory Alternatives.
Treasury Board Secretariat, RIAS Writer’s Guide. August 1992.
APPENDIX I - SAMPLE STAKEHOLDER LIST
^
GENERIC STAKEHOLDER LIST |
INTERNAL STAKEHOLDER |
EXTERNAL STAKEHOLDER |
AUTHORITY PILOTS |
CANADIAN COAST GUARD - FISHERIES AND OCEANS |
BOARD OF DIRECTORS |
COASTAL ENTERPRISES |
CHEF EXECUTIVE OFFICER |
CORPORATIONS (PRIVATE) |
DISPATCHING PERSONNEL |
ENVIRONMENTAL GROUPS |
OPERATIONAL STAFF |
MINISTER OF TRANSPORT CANADA (REGULATORY) |
PILOTAGE MANAGEMENT |
PASSENGER SHIP OWNERS - OPERATORS |
|
PILOTAGE UNIONS/ASSOCIATIONS |
|
PORT AND HARBOR AUTHORITIES |
|
PROVINCIAL GOVERNMENTS |
|
SHIP OWNERS/ OPERATORS |
|
TOWING COMPANIES |
|
US PILOTAGE AUTHORITIES/ORGANIZATIONS |
WORKSHEET CHECKLIST ^
|
WORKSHEET TITTLE |
WORKSHEET REFERENCE
NUMBER |
STATUS |
NATURE AND SCOPE OF DECISION |
1.1 |
|
IDENTIFY ISSUES |
1.1.1 |
|
DEFINE LIMITS AND PRIORITIES |
1.1.4 |
|
RISK MANAGEMENT TEAM |
1.1.6 |
|
STAKEHOLDER ANALYSIS |
1.2 |
|
STAKEHOLDER IDENTIFICATION |
1.2.1 |
|
PROFILES OF STAKEHOLDERS AND NICS |
1.2.2 |
|
RISK SCENARIOS |
2.1 |
|
HAZARD IDENTIFICATION |
2.1.1 |
|
DESCRIPTION OF RISK SCENARIOS |
2.1.2 |
|
RISK ESTIMATION |
2.2 |
|
RISK MATRIX |
2.2.2 |
|
RISK EVALUATION |
2.3 |
|
IDENTIFICATION OF DEFENCES |
2.3.1 |
|
DEFENCE EFFECTIVENESS |
2.3.2 |
|
ACCEPTABILITY TO STAKEHOLDERS |
2.3.3 |
|
RISK CONTROL STRATEGIES |
2.4 |
|
IDENTIFY FEASIBLE OPTIONS |
2.4.1 |
|
IMPACT ON IDENTIFIED NICS |
2.4.3 |
|
IMPLEMENTATION |
3.1 |
|
COMMUNICATION PLAN |
3.1.2 |
|
INITIATION MODULE ^ |
NATURE AND SCOPE OF DECISION |
WORKSHEET
1.1 |
PROJECT NUMBER: |
DATE: |
NATURE OF DECISION: |
GO |
NO GO (EXPLAIN WHY) |
OBJECTIVES |
TIME
FRAME TEAM
REQUIRED?
START END
YES NO |
|
|
|
|
|
|
|
|
|
|
|
|
AUTHORITY: |
INITIATION MODULE ^
|
IDENTIFY ISSUES |
WORKSHEET 1.1.1 |
SITUATIONAL QUESTIONS
|
HOW DO YOU KNOW THIS? |
What is happening? |
|
What is the normal situation? |
|
Why is it a problem or a concern? |
|
Is this a concern for your organization? |
|
How did this situation develop? |
|
Where does it happen? |
|
When does it happen? |
|
What are the circumstances around the issues? |
|
With whom is it happening or who could be affected by this
concern? (Stakeholder worksheet) |
|
BASED ON ALL OF THE ABOVE, ARTICULATE A QUESTION THAT WILL
CLEARLY IDENTIFY THE NATURE OF THE DECISION. |
AUTHORITY: |
INITIATION MODULE ^ |
DEFINE LIMITS AND PRIORITIES |
WORKSHEET 1.1.4 |
PROJECT NUMBER: |
DATE: |
NATURE OF DECISION: |
OBJECTIVES: |
LIST THE TASK |
SEQUENCE |
CONSTRAINTS |
START |
END |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AUTHORITY: |
INITIATION MODULE ^ |
RISK MANAGEMENT TEAM |
WORKSHEET 1.1.6 |
PROJECT NUMBER: |
DATE: |
NATURE OF DECISION: |
OBJECTIVES: |
TASK REQUIRED? |
CAPABILITY REQUIRED? |
TEAM MEMBER |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AUTHORITY: |
INITIATION MODULE ^ |
STAKEHOLDER ANALYSIS |
WORKSHEET 1.2 |
PROJECT NUMBER: |
DATE: |
NATURE OF DECISION: |
NAME |
NEEDS, ISSUES AND CONCERNS |
AFFECTED
YES NO |
CONSULTED
YES TO DO NO |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AUTHORITY: |
INITIATION MODULE ^ |
STAKEHOLDER ANALYSIS |
WORKSHEET 1.2.1 |
PROJECT NUMBER: |
DATE: |
NATURE OF DECISION: |
NAME |
ORGANIZATION |
AFFECTED
YES NO |
CONSULTED
YES TO DO NO |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AUTHORITY: |
INITIATION MODULE ^ |
PROFILE OF STAKEHOLDER AND NICs |
WORKSHEET 1.2.2 |
PROJECT NUMBER: |
DATE: |
STAKEHOLDER: |
Needs in relation to the decision to be taken?
|
Do they know, believe, or perceive that they
will be affected?
|
How will this positively affect them?
|
How will this negatively affect them?
|
What is their current knowledge/understanding of
the issues? Are there any gaps?
|
Do they have any impact on the decision? If so,
explain.
|
Concerns in relation to the decision to be
taken?
|
Any misperceptions regarding the decision to be
taken?
|
Do you need to consult with this stakeholder?
Explain.
|
AUTHORITY: |
RISK ASSESSMENT MODULE ^ |
RISK SCENARIOS |
WORKSHEET 2.1 |
NATURE OF DECISION: |
NAME |
SCENARIOS
(What if + So what + How often)
|
AFFECTED
|
Scenario
NUMBER |
Consulted
|
Keep
|
YES |
NO |
TO DO |
YES |
NO |
|
|
|
YES |
NO |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AUTHORITY: |
RISK ASSESSMENT MODULE ^ |
HAZARD IDENTIFICATION |
WORKSHEET 2.1.1 |
PROJECT NUMBER: |
DATE: |
NATURE OF DECISION: |
HAZARD DESCRIPTION |
NATURAL |
HUMAN |
ECONOMIC |
TECHNICAL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AUTHORITY: |
RISK ASSESSMENT MODULE ^ |
DESCRIPTION OF RISK SCENARIOS |
WORKSHEET 2.1.2 |
PROJECT NUMBER: |
DATE: |
NATURE OF DECISION: |
HAZARD: |
SCENARIOS: |
WHAT IF
(CONDITION) |
SO WHAT
(CONSEQUENCE/ SEVERITY) |
HOW OFTEN
(FREQUENCY/PROBABILITY) |
|
|
|
STAKEHOLDER AFFECTED |
NEED TO BE CONSULTED
|
NO |
TO DO |
DONE |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AUTHORITY: |
RISK ASSESSMENT MODULE ^ |
Risk
Estimation |
WORKSHEET
2.2 |
Project Number: |
Date: |
Nature OF DECISION:
|
Number
|
Scenario |
Probability |
Severity |
Risk Level |
Extreme |
Hight |
Medium |
Low |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AUTHORITY: |
RISK ASSESSMENT MODULE ^ |
RISK MATRIX |
WORKSHEET 2.2.2 |
PROJECT NUMBER: |
DATE: |
NATURE OF DECISION: |
SCENARIO: |
SCENARIO NUMBER: |
CATEGORY |
DESCRIPTION OF PROBABILITY OF ADVERSE CONSEQUENCES OVER TIME |
Highly Probable |
|
Probable |
|
Unlikely |
|
Improbable |
|
CATEGORY |
DESCRIPTION OF SEVERITY OF ADVERSE CONSEQUENCES |
Catastrophic |
|
Major |
|
Minor |
|
Negligible |
|
Severity of Adverse Consequences
|
Probability of Adverse
Consequence Over Time |
Highly
Probable |
Unlikely Improbable |
Unlikely |
Improbable |
CATASTROPHIC |
Extreme |
Hight |
Medium |
Medium |
MAJOR |
Hight |
Hight |
Medium |
Medium |
MAJOR |
Medium |
Medium |
Medium |
Low |
NEGLIGIBLE |
Low |
Low
|
Low |
Low |
AUTHORITY:![](/web/20060212065411im_/https://www.tc.gc.ca/marinesafety/TP/TP13741/13741-images/Commun1.gif)
RISK ASSESSMENT MODULE ^
|
RISK EVALUATION |
WORKSHEET 2.3 |
PROJECT NUMBER: |
DATE: |
NATURE OF DECISION: |
Scenario
Number
|
Risk Level |
Defences |
% Effect |
Acceptable
|
Action
Required
|
Yes |
No |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AUTHORITY: |
|
RISK ASSESSMENT MODULE ^ |
IDENTIFICATION OF DEFENCES |
WORKSHEET 2.3.1 |
PROJECT NUMBER: |
DATE: |
NATURE OF DECISION: |
HAZARD: |
SCENARIO: |
CURRENT PHYSICAL DEFENCES |
On the source (of risk) |
On the human or object (target) |
Between unsafe condition and the target |
System design & manufacture |
Repair & overhaul |
CURRENT ADMINISTRATIVE DEFENCES ^ |
Operational readiness
(Risk assessment, system support
services, fitness of organization for mission) |
Personal readiness (Qualifications, knowledge,
experience, fitness for duty) |
Team readiness (Qualifications, knowledge,
experience, fitness for duty) |
Information system (Technical information for
operation, information on safe operating
procedures, and practices) |
Training and awareness |
Inspection and preventive maintenance |
Supervision, performance monitoring,
and corrective action |
Company procedures |
Company manning policies |
Company management philosophy |
Regulatory policies |
Legislation |
Regulations |
Regulatory implementation |
Regulatory surveillance, inspection, and audit |
Regulatory enforcement |
Codes, standards, guidelines |
Incentives (positive incentives, negative
incentives, etc.) |
Emergency preparedness |
AUTHORITY: |
RISK ASSESSMENT MODULE ^ |
DEFENCE EFFECTIVENESS |
WORKSHEET 2.3.2 |
PROJECT NUMBER: |
DATE: |
NATURE OF DECISION: |
SCENARIO: |
SCENARIO NUMBER: |
DEFENCES |
EFFECT ON FREQUENCY |
EFFECT ON SEVERITY |
ESTIMATED%EFFECT
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AUTHORITY: |
RISK ASSESSMENT MODULE ^ |
ACCEPTABILITY TO STAKEHOLDERS |
WORKSHEET 2.3.3 |
PROJECT NUMBER: |
DATE: |
NATURE OF DECISION: |
SCENARIO: |
SCENARIO NUMBER: |
RISK LEVEL:__________ |
STAKEHOLDER |
ACCEPTABILITY OF RISK |
ADDRESS IN COMMUNICATION PLAN |
YES |
NO |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AUTHORITY: |
RISK ASSESSMENT MODULE ^ |
RISK CONTROL STRATEGIES |
WORKSHEET 2.4 |
PROJECT NUMBER: |
DATE: |
NATURE OF DECISION: |
SCENARIO
NUMBER
|
SELECTED
DEFENCES
|
PREVIOUS
RISK LEVEL
|
NEW RISK
LEVEL
|
IMPACTON NICs
|
ACCEPTABLE
|
YES |
NO |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AUTHORITY: |
RISK ASSESSMENT MODULE ^ |
IDENTIFY
FEASABLE OPTIONS |
WORKSHEET
2.4.1 |
PROJECT NUMBER: |
DATE: |
NATURE OF DECISION: |
SCENARIO
NUMBER: |
CURRENT
RISK LEVEL: |
PHYSICAL |
DEFENCES |
PROBABILITY |
SEVERITY |
RISK LEVEL |
On the source (of risk) |
|
|
|
|
On
the human or object (target) |
|
|
|
|
Between
unsafe condition and the target |
|
|
|
|
System
design & manufacture |
|
|
|
|
Repair
& overhaul |
|
|
|
|
ADMINISTRATION |
DEFENCES |
PROBABILITY |
SEVERITY |
RISK
LEVEL |
Operational readiness (Risk assessment, system support
services, fitness of organization for mission) |
|
|
|
|
Personal readiness (Qualifications, knowledge,
experience, fitness for duty) |
|
|
|
|
Team readiness (Qualifications, knowledge, experience,
fitness for duty) |
|
|
|
|
Information system (Technical information for operation,
information on safe operating procedures, and practices) |
|
|
|
|
Training and awareness |
|
|
|
|
Inspection and preventive maintenance |
|
|
|
|
Supervision, performance monitoring,
and corrective action |
|
|
|
|
Company procedures |
|
|
|
|
Company manning policies |
|
|
|
|
Company management philosophy |
|
|
|
|
Regulatory policies |
|
|
|
|
Legislation |
|
|
|
|
Regulations |
|
|
|
|
Regulatory implementation |
|
|
|
|
Regulatory surveillance, inspection,
and audit |
|
|
|
|
Regulatory enforcement |
|
|
|
|
Codes, standards, guidelines |
|
|
|
|
Incentives (positive incentives,
negative incentives, etc.) |
|
|
|
|
Emergency preparedness |
|
|
|
|
AUTHORITY: |
RISK ASSESSMENT MODULE ^ |
IMPACT ON IDENTIFIED NICS |
WORKSHEET 2.4.3 |
PROJECT NUMBER: |
DATE: |
NATURE OF DECISION:
|
SCENARIO: |
FEASIBLE OPTION: |
STAKEHOLDERS |
NEEDS, ISSUES AND CONCERNS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AUTHORITY: |
ACTION MODULE ^ |
IMPLEMENTATION |
WORKSHEET 3.1 |
PROJECT NUMBER:
|
DATE: |
NATURE OF DECISION:
|
RISK CONTROL OPTION |
RESPONSIBILITY |
START |
END |
PERFORMANCE INDICATOR |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AUTHORITY: |
ACTION MODULE ^ |
PROJECT NUMBER: |
DATE: |
NATURE OF DECISION:
|
TARGET GROUP |
COMMUNICATION OBJECTIVES |
MESSAGE |
TIMING |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AUTHORITY: |
INITIATION MODULE
THE PILOTAGE RISK MANAGEMENT METHODOLOGY
STEPS OF THE PROCESS
INITIATION MODULE ^
![INITIATION MODULE](/web/20060212065411im_/https://www.tc.gc.ca/marinesafety/TP/TP13741/13741-images/initiation-module-1.gif)
RISK ASSESSMENT MODULE ^
ACTION MODULE ^